Get perfect grades by consistently using our writing services. Place your order and get a quality paper today. Take advantage of our current 20% discount by using the coupon code GET20
Order a Similar Paper Order a Different Paper
In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.
Activity Task Predecessors Duration Activity Cost A Sign Contract None 5 days $5,000 B Design Survey A 3 days $1,500 C Identify Audience A 7 days $1,000 D Run Survey B, C 30 days $6,000 E Analyze Results D 5 days $3,000 F Create Presentation E 5 days $1,000 G Present to Client E, F 2 days $3,000
- Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module’s lecture.
- What is the duration of the project?
- How much slack is currently available in the non-critical path?
- How long are the project and feeder buffers?
Got stuck with another paper? We can help! Use our paper writing service to score better grades and meet your deadlines.
Get 15% discount for your first order
Order a Similar Paper Order a Different Paper
